Underbank Newsletter Updates - June 2026
Underbank Construction Updates
River View
Stage S1301 is complete.
Park View
Construction of Stages 21–22 is complete.
Council requested an additional landscape plan and bond for Stage 21, which had not been mentioned previously. However, the final landscape agreement has now been signed and submitted to Council. The SOC is expected to be issued shortly.
Stage 23 construction will resume after the Stage 21 overhead power line is retired on 19 Aug 26, with completion expected around eight weeks. Stages 23 and 24 are forecast to settle in Nov 2026.
Town Centre
The Moorabool Shire Retail Strategy is expected to receive Ministerial approval in late 2026, after which Council will be able to proceed with the Town Centre rezoning process.
Sports Precinct
The planning permit approval is expected shortly.

River View (S901 Townhouse)

Stage S901 Townhomes – The balance of S901 building construction is underway and nearing completion.
River View (S1301)

Construction works for Stage S1301 is complete.
Park View (21-24)

All major estate works are all complete.
Stage 21 & 22 rectification works and final inspections by Council and the relevant serivce authorities are all completed. Now the SOC is waiting for the final Council adminstrative process


All the major Estate works on Randwick Avenue are all complete.
We anticipate achieving Statement of Compliance (SOC) by the November 2026.
We thank you for your continued support and patience, and look forward to sharing more exciting updates with you soon.