Underbank Newsletter Updates - June 2026

 

Underbank Construction Updates

     

River View

Stage S1301 is complete. 

 
Park View

Construction of Stages 21–22 is complete. 

Council requested an additional landscape plan and bond for Stage 21, which had not been mentioned previously. However, the final landscape agreement has now been signed and submitted to Council. The SOC is expected to be issued shortly.

Stage 23 construction will resume after the Stage 21 overhead power line is retired on 19 Aug 26, with completion expected around eight weeks. Stages 23 and 24 are forecast to settle in Nov 2026. 

 

Town Centre

The Moorabool Shire Retail Strategy is expected to receive Ministerial approval in late 2026, after which Council will be able to proceed with the Town Centre rezoning process.

 

Sports Precinct

The planning permit approval is expected shortly.

 June

 

River View (S901 Townhouse)

 

 S901

Stage S901 Townhomes – The balance of S901 building construction is underway and nearing completion.

 

 

River View (S1301)

DJI_0967

Construction works for Stage S1301 is complete.

 

 

 

Park View (21-24) 

 

 

DJI_0968

All major estate works are all complete.

Stage 21 & 22 rectification works and final inspections by Council and the relevant serivce authorities are all completed. Now the SOC is waiting for the final Council adminstrative process

 

DJI_0972

 

DJI_0978

All the major Estate works on Randwick Avenue are all complete. 

We anticipate achieving Statement of Compliance (SOC) by the November 2026.

 

 

We thank you for your continued support and patience, and look forward to sharing more exciting updates with you soon.

 

 

 

 

 

 

 