Underbank Newsletter Updates - June 2025
Underbank Construction Updates
We’re pleased to share an exciting update on the progress of your future community.
River View
Earthworks have commenced for Stage S1301.
Park View
We have commenced construction of the culvert and associated creek works on 23 June 2025. These works are designed to enhance stormwater management, improve natural flow paths, and contribute to a sustainable and visually appealing environment throughout the estate.
Town Centre
We are currently in the process of rezoning the town center land to commercial use. The Council has requested an indicative layout, which has been prepared by our planning consultant. Additionally, we have engaged a consultant to design the retail component and layout.
We thank you for your continued support and patience, and look forward to sharing more exciting updates with you soon.
River View (S901 Townhouse)
Stage S901 settlements have been completed, and owners have begun construction.
River View (S1301)
Earthworks have commenced for Stage S1301.
Park View (21-24)
Recently received the Works offer from Melbourne Water. We have commenced construction of the culvert and associated creek works on 23 June 2025.